I'm planning the SU2 upgrade for my 8.02 UCCX cluster.
How much can I do during business hours? We're a low volume call center, so I'm not concerned about load.
Can I upload the image to the inactive on node1, then also on node2? And then of course once I do the switch version on node1 our outage would begin.
-Bill-
Solved! Go to Solution.
01-19-2011 03:24 AM
Hi Bill
You can run the install during production hours however ensure that you don't set it to restart/switch version upon the install.
As for node 2 I haven't had the opportunity to test wither you can upgrade 2 nodes yet without the switch version however this should atleast get your call center up and running on one node once the switch version is complete.
Regards
Hoai Huynh
01-19-2011 05:07 AM
As Hoai said, you can do the upgrade during production. The procedure is upgrade node1, once complete, upgrade node2. Then wait for your outage window. Switch version on node1, once complete, switch version on node2. Rerun desktop config tool. Update clients.
01-19-2011 03:24 AM
Hi Bill
You can run the install during production hours however ensure that you don't set it to restart/switch version upon the install.
As for node 2 I haven't had the opportunity to test wither you can upgrade 2 nodes yet without the switch version however this should atleast get your call center up and running on one node once the switch version is complete.
Regards
Hoai Huynh
01-19-2011 05:07 AM
As Hoai said, you can do the upgrade during production. The procedure is upgrade node1, once complete, upgrade node2. Then wait for your outage window. Switch version on node1, once complete, switch version on node2. Rerun desktop config tool. Update clients.