03-08-2016 02:18 AM - edited 03-14-2019 03:51 PM
Dear Experts,
I'm planning to have a CVP Upgrade from 9 .0 to 10.5 for one of our customers.
I already did the upgrade in my lab and I'm planning the below for the customer:
- Upgrade CVP Reporting server and Operations Console during working hours as they don't affect the Call Flow.
- Upgrade both CallVXMLA and CallVXMLB in a maintenance window.
My concern is the RollBack Plan in case something didn't go as expected.
Has someone faced such an issue?
Thanks is advance.
08-10-2016 01:30 AM
Hi laranoueir,
I am also planning same upgrade from 9.0 to 10.5 (common ground upgrade). please let me know if you received any rollback plan for this upgrade.
-Thanks
08-10-2016 02:03 AM
Hello,
Actually there is no roll back plan as all what you will do is to run the CVP upgrade installation.
As far as I remember, we have faced an issue after upgrading Call/VXML sideB where the call server service didn't go up after the upgrade and we were obliged to uninstall CVP and re-install it again from scratch.
I hope things will go smoothly with you. Let us know how it goes.