IPCC/UCCX wrap-up time automatic work

if automatic work is enabled can the agent interrupt the "Work" state after a call to force themself into Not Ready? I can't seem to find an answer for this question, the customer would like the agents to be able to override the automatic work timer if they need more time.

1 ACCEPTED SOLUTION

Accepted Solutions
Highlighted

Re: IPCC/UCCX wrap-up time automatic work

While in a Work state, an agent does have the option for going Not Ready as long as they do so prior to the timeout expiring.

2 REPLIES 2
Contributor

Re: IPCC/UCCX wrap-up time automatic work

You cannot configure a wrap-up delay for an agent in Customer Response Solutions (CRS) versions prior to CRS 4.0. This is a new feature which is introduced in CRS 4.0. There is a work-around to allow the Aagent to automatically have a delay before accepting the next call. To do this, modify the IVR script as shown:

On the Interactive Voice Response (IVR) script you are using to route the calls from the queue to an agent, find the Select Resource Step and change the Connect property to No.

Under the Select Resource Step you modified, there is a Selected step. Add a Delay step (The time should be the wrap-up time you want to configure. For example, 30 seconds), and then a Connect step.

Verify in CRS AppAdmin that all Integrated Contact Distribution (ICD) resources have Automatic Available set to Enabled.

Verify in CRS AppAdmin that all the ICD Contact Service Queues (CSQs) have Automatic Work set to Disabled.

This is the expected behavior of the agents:

The agent ends the previous call and goes into Ready state.

The agent is selected to accept the next call, and the agent is put in a Reserved state.

The IVR script hits the 30 second delay. This gives the agent 30 seconds in the Reserved state.

After the delay ends, the call is routed to the agent.

Highlighted

Re: IPCC/UCCX wrap-up time automatic work

While in a Work state, an agent does have the option for going Not Ready as long as they do so prior to the timeout expiring.

CreatePlease to create content
Content for Community-Ad
August's Community Spotlight Awards