We are in process of upgrading PCCE from 10.5 to 11.6.
As per docs it looks like it’s a to step upgrade
- upgrade 10.5 to 11.0
- upgrade 11.0 to 11.6
I think if it's possible to do it this way.
Upgrading all components on Side A, first to 11.0 then to 11.6.
Cutting over from Side A to Side B
Upgrading all components on Side B, first to 11.0 then to 11.6.
Synchronizing Side A and Side B
Anyone please confirm if upgrade side A of PCCE from 10.5 to 11.0 and to 11.6 and then upgrade side B of PCCE from 10.5 to 11.0 and to 11.6 is possible ?