PCCE upgrade from 10.5 to 11.6

Soeren Hoegedal
Level 1
Level 1

We are in process of upgrading PCCE from 10.5 to 11.6.

 

As per docs it looks like it’s a to step upgrade

  1. upgrade 10.5 to 11.0
  2. upgrade 11.0 to 11.6

 

I think if it's possible to do it this way.

Upgrading all components on Side A, first to 11.0 then to 11.6.

Cutting over from Side A to Side B

Upgrading all components on Side B, first to 11.0 then to 11.6.

Synchronizing Side A and Side B

 

Anyone please confirm if upgrade side A of PCCE from 10.5 to 11.0 and to 11.6 and then upgrade side B of PCCE from 10.5 to 11.0 and to 11.6 is possible ?

1 Reply 1

Omar Deen
Spotlight
Spotlight

Yes, it's possible as long as you're okay with the risks involved.