Hi
I have Fex N2K-C2232PP connected to EOL Leaf , i have added a new Leaf to my fabric and I'm trying to migrate ( connect FEX to my new leaf ) . i know FEX is not recommended anymore in CISCO but this is a temporary setup until some of DC servers are decommissioned.
in order to do that all i have to do is to remove the uplinks from OLD Leaf and terminate them to my new leaf ( Fex connected to new Leaf ) . The traditional way is to start changing the objects static port paths in each EPG for example : from OldLeaf-Fex101-eth1/1 to Newleaf-Fex101-eth1/1 once the uplinks have been migrated as the new leaf has no extended interfaces from the fex yet . i was wondering if this is the best scenario or is there a better way to proceed with this migration just to avoid any misconfiguration as we have limited time for our migration ?
Thanks