Keep adding a day to a static date.

Michael Durette
Level 1
Level 1

Hello....

I'm looking to do the following:

01/01/2013

+1

01/02/2013

+1

01/03/2013

and so on to 05/16/2013

So the job I'm running will repeat 135 times.

I've tried calculate date, but all I get is 01/01/2013 to 01/02/2013.

That you for this help....

We are running 5.3.1.374 Tidal

Even if I need to run a unix script and fill a variable that will be fine.

1 Reply 1

Michael Durette
Level 1
Level 1

I was WAY over thinking this issue. Kind of.

The date format was 20130101 and I needed to 1and increment by 1.

I created a variable to do a +1 then I would run the job 30 or 31 times depending on how many days in the month.

Then I would manually change the variable to 20130201 and run the next month. It is still a manual process 12 times, but at least we didn't do it for every day.

Thank you to the 26 who have viewed this post.

Resolved.