08-21-2008 07:19 AM
just upgraded LMS 3.0 to 3.1
server is running solaris 5.10
LMS is integrated with ACS 4.1
cannot run IPM as process is down.
if I start the process manually it
is shutdown after a few seconds.
all other processes including an evaluation copy of HUM are working
normally.
any ideas?
Solved! Go to Solution.
08-22-2008 07:58 AM
Looks like a problem with your IPM database caused by the migration (or perhaps a patch you had applied to IPM 4.0.1). If you don't have any data in this database you need preserved, you can simply reinitialize it:
NMSROOT/bin/perl NMSROOT/bin/dbRestoreOrig.pl dsn=ipm dmprefix=Ipm
If you do have data to preserve, you'll need to contact the TAC to correct this problem as it will involve some direct database access.
08-21-2008 07:21 AM
Please post the output of the /opt/CSCOpx/bin/pdshow command.
08-21-2008 07:46 AM
08-21-2008 09:42 AM
Please post the ipmprocess.log and the daemons.log.
08-21-2008 11:59 PM
08-22-2008 07:58 AM
Looks like a problem with your IPM database caused by the migration (or perhaps a patch you had applied to IPM 4.0.1). If you don't have any data in this database you need preserved, you can simply reinitialize it:
NMSROOT/bin/perl NMSROOT/bin/dbRestoreOrig.pl dsn=ipm dmprefix=Ipm
If you do have data to preserve, you'll need to contact the TAC to correct this problem as it will involve some direct database access.
08-24-2008 11:26 PM
Thanks again for all of your help