FCoE Configuration? N55-M16UP add modules after Nexus5548UP

Hi.

N55-M16UP add modules after setting the Nexus5548UP

After installing the interface module that is automatically generated?

Do I need to reboot during FCoE interface settings?

Feature FCoE  is enabled.

Thank's

Everyone's tags (1)
3 REPLIES 3
Highlighted
Beginner

Jongsu,

Jongsu,

I am getting ready to install 2 N55-M16UP units to 2 5548UPs. Were they hot swappable and did you need to reboot the units

Thanks,

Tom

Highlighted
Advocate

Hi Tom

Hi Tom

see http://www.cisco.com/c/en/us/td/docs/switches/datacenter/nexus5000/hw/installation/guide/nexus_5000_hig/overview5500.html#18319

You can hot swap the expansion modules during operations, except the Layer 3 GEMs. You must power down the switch before you can insert or remove the Layer 3 GEMs.