Datacenter Core (layer 2 and layer 3 ) VDC migration to nexus 9300

Mudas_2019
Level 1
Level 1

We are planning to migrate the nexus switch 7004 to nexus 9300 switches  . We have three vdc (one admin , one layer 2 core and one layer3 )  . I am doing ist time datacenter core migration . 

 

What all precaution we have to take  ? 

what will be the mapping one vdc to one 9k device  ?  

any document i have to follow ?  

 

1 Reply 1

balaji.bandi
Hall of Fame
Hall of Fame

VDC is nothing but slicing the chasis to different line cards.

you no need to worry admin vDC that is for management.

 

Are you looking each VDC different nexus 9300 ?  and vPC

 

Make a small chart and port config, Migration approach port by port.

 

you need to look as below :

 

Look at Layer 2 vDC - to Layer2 config in nexus 9300 acting as layer2

Look at Layer 3 vDC - to Layer3 config in nexus 9300 acting as layer3

BB