Hi Team,I am filling one RFP, i am not familliar in doing it ,actually doing it first time,, there are two questions which i am unable to understand  completely.

Can someone please elaborate it for me?

8.26 Do you have a multi-tiered network topology that segregates presentation, application and data layers?

8.27 Do you have a secure network connection that is segregated form the production environment for administration and data transfers?

8.37 Do you have security administration procedures and processes for managing the access of the services provided?

3 Replies 3

donlindsay70
Level 1
Level 1

8.26 is probably refering to the e-commerce style separation between web/application/database architecture. See Network Design for B2B and B2X Server Farms in the pdf.

http://www.cisco.com/en/US/docs/solutions/Enterprise/Data_Center/ServerFarmSec_2.1/2_Topolo.pdf

8.27 - probably asking if you have a separate out-of-band data network for management which is also secure ie SSH etc.

8.37 - see IT processes such as ISO 27001/2 for administration controls and auditing.

stephenshaw
Level 1
Level 1

Hi,

8.27 could also be referring to a DMZ firewalled environment.