I have 2 units core swicth C4510R+E SUP7-E need to connect together for redundant purpose , i bought also 4X 10GE uplinks for each core switches .
May i know how i shall connect both core switches together using my spec Catalyst 4500 E-Series 12-Port 10GbE (SFP+) ?
Thank you
11-05-2012 07:12 PM
The best method to connect two switches is using VSS. Unfortunately, VSS for the Sup7E is "not yet" available. There are rumours about something coming out before the end of December 2012. Otherwise, the IOS that will support VSS on a Sup7E might come out on March 2013.
For the time being, you can settle with HSRP/VRRP.
11-05-2012 07:57 PM
What shall i do on the physical connection to provide best redundancy?
How about of physical connection, how should i connect?
Below is the graphic of the C4510R+E
11-05-2012 08:20 PM
One 10 Gbps link (each) on the supervisor card going to the other.
11-05-2012 08:53 PM
I think it's better to configure between them EtherChannel bundle and configure it as a trunk.
Abzal
11-05-2012 10:30 PM
How about refer to below? Shall i connect both core switch parallel or cross connect?
11-12-2012 01:14 AM
Hi Anyone know how to connect?
Discover and save your favorite ideas. Come back to expert answers, step-by-step guides, recent topics, and more.
New here? Get started with these tips. How to use Community New member guide