03-07-2025 07:25 AM
After taking a Data Export the existing database is essentially frozen. Is there any way to carry out a further export/import after the new cluster has been built without rebuilding all of the nodes. I have a gap of over a week between original export/import and the go live and customer has not logged any changes.
Solved! Go to Solution.
03-07-2025 10:41 AM
Hi Paul,
Data export/import is a one shot deal, there's no ability for data "top off" at a later time.
Brad
03-07-2025 10:41 AM
Hi Paul,
Data export/import is a one shot deal, there's no ability for data "top off" at a later time.
Brad
03-09-2025 03:04 AM
You cannot import the data exported after a new cluster has been built. To use the exported data, you must select the appropriate option during installation.