Hello,

 

I want to Schedule Backup of CUCM from the DRS GUI interface, but status shows: Update Failed. The configured date or time has elapsed.  

 

Schedule Backup from CLI and its completes successfully.

 

I see that 2 hours are show, the first one refers to CST and the other one to UTC as shown in the following image:

Bcku.jpg

Why?

 

I would like to Schedule Backup of CUCM from the DRS GUI interface without  issue.

 

Regards,

 

2 Replies 2

HI Aimee

 

did you resolve this issue?
I have the same error.

 

Regards

Cristian,

 

Check your Date/Time group configuration under CUCM admin. System >>> Date/Time Group. It defaults to UTC even though your times may be correct everywhere else in the system.

 