04-01-2010 02:46 AM - edited 03-19-2019 12:43 AM
Hi All,
I'm just wondering if anybody could help me on that case.
We have Unity Connection running with a nightly scheduled backup process. Now I was told that since one week ago the Unity won't write new backup files. That was absolutely correct as I looked on the system the backup process was still ongoing. So I decided to cancel the job but this doesn't brought success at all. I've canceled the process yesterday and it is still running.
Now I want to ask if somebody had the same experiences made or knows how to resolve this issue easily.
Many thanks in advance,
Cheers
Michael
Solved! Go to Solution.
04-01-2010 04:14 AM
Hi
You can go into Serviceability/Control Centre - Network Services and find the DRF Master and DRF Local services. Restart those, and that should clear the stuck backup.
Regards
Aaron
Please rate helpful posts...
04-01-2010 04:14 AM
Hi
You can go into Serviceability/Control Centre - Network Services and find the DRF Master and DRF Local services. Restart those, and that should clear the stuck backup.
Regards
Aaron
Please rate helpful posts...
04-01-2010 05:04 AM
Hi,
thank you very much. This post helps me out. Works perfect.
Thanks.
Cheers
Michael
02-24-2017 11:41 AM
Hi,
This is really helpful for my day to day backup processes.
Thanks Cisco Gurus
03-17-2017 01:33 AM
Good to hear, if it's useful please rate the post ;-)
Find answers to your questions by entering keywords or phrases in the Search bar above. New here? Use these resources to familiarize yourself with the community: