Blade move procedure

Andreas Linde
Level 1
Level 1

Hi,

What is the recommended process for moving a provisioned blade (B230 M1) to a new set of FI/Chassi?
The new platform has a service profile template created and a B230 M4 blade already provisioned.

 

Would the first step be to decommission the blade i the old FI? Then what? Move to the new chassi, let it be discovered and then apply the same template as for the M4 blade?

 

Cheers!

 

 

1 Accepted Solution

Accepted Solutions

Keny Perez
Level 8
Level 8

It would be:

-Disassociate the Service Profile  (SP)

-Decommission the blade

-Remove the blade

-Install it in the new chassis and let the system discover it

-Assign a new SP

 

Be careful your system has the proper firmware to support the server and the OS. This will help you out: http://www.cisco.com/web/techdoc/ucs/interoperability/matrix/matrix.html

 

Rate if helpful.

-Kenny

 

View solution in original post

1 Reply 1

Keny Perez
Level 8
Level 8

It would be:

-Disassociate the Service Profile  (SP)

-Decommission the blade

-Remove the blade

-Install it in the new chassis and let the system discover it

-Assign a new SP

 

Be careful your system has the proper firmware to support the server and the OS. This will help you out: http://www.cisco.com/web/techdoc/ucs/interoperability/matrix/matrix.html

 

Rate if helpful.

-Kenny

 