05-14-2013 09:13 AM - edited 07-04-2021 12:04 AM
We have 2 WiSM's in 2 different data centers and a 4402 and 5508 anchor in the main data center.
Data Center A:
WiSM
4402
5508
Data Center B:
WiSM
I need to update all controllers to 7.0.240.0. Is there a way to do this without an outage on the WiSMs?
We have AP failover set up, but is there an easy way to force all AP's to one controller so I can upgrade the other, and then force back so the AP's will only upgrade code once?
Or is it best to do them both at the same time and pre-download the image to the AP's?
We do not have redundancy for the anchors, so there will be an outage for those.
05-14-2013 09:38 AM
I would just use image pre-download.
otherwise you would need to set the primary on the AP's. if you want to do that, I'd use a WCS template so you can revert easily
HTH,
Steve
------------------------------------------------------------------------------------------------
Please remember to rate useful posts, and mark questions as answered
05-14-2013 01:52 PM
I did the pre-download and set them to boot after business hours.
Thanks for the advice.
05-14-2013 05:52 PM
Be very aware that doing the predownload and cause and will often cause the aps to drop from the wlc ..
Sent from Cisco Technical Support iPhone App
05-14-2013 05:57 PM
Didn't seem to have an issue today.