03-28-2016 08:42 AM - edited 03-01-2019 09:21 AM
I have a job event that inserts a job when associated jobs complete abnormally, the first step of the job that is inserted has a 20 wait time, the second step restarts the original failed job id. This process will however rerun everytime the job fails. Is there a way to limit the amount of times the job event can insert a job for this? Hope this makes sense
03-28-2016 09:26 AM
Hi Thomas,
You can directly associate a job re-run action and specify up to X many times to the completed abnormally job event.
BR,
Derrick Au
03-28-2016 10:46 AM
I have a few jobs setup like this already but the rerun occurs one after another without pausing or waiting for say 15 minutes.
03-28-2016 10:58 AM
I followed a procedure https://supportforums.cisco.com/discussion/12614411/rerun-job-after-delay I found a document on this forum for setting a delayed job and it works well but will continue to rerun until the job has completed normally. I have a customer who only wants their jobs rerun once so I would like to limit the delayed start job to running once.
03-28-2016 02:21 PM
Hi Thomas,
I will have to get back to you on this one.
03-29-2016 04:34 AM
Thanks Derrick
03-29-2016 07:23 AM
03-29-2016 10:30 AM
Derrick, I'll check with my team and see if they can clarify a few things for me. I'll let you if we get it working