Hi everyone,Catalyst Center !!I need to upgrade 10 switches tonight: 1 border switch, 2 distribution switches, and the remaining access switches spread across 4 floors.How would you approach this upgrade? How long does an upgrade approximately take i...
Hi everyone,I've noticed the following issue. I have two border routers (sb1 & sb2).One of them displays "Not Provisioned", while the other shows "Expired".Does anyone have an idea how I can resolve this issue?Best regards,Salvatore
Hello everyone,I have the following situation and would like to know what the best approach would be.I have switch stacks in several patch rooms. After reviewing the setup, I realized that I don't need that many ports, so I would like to remove one s...
Hello everyone,I have a strange phenomenon which is probably just a minor issue.I am using the following configuration in the CLI template: !banner motd ^C***************************************************** !!Device is managed by DNA-Center!! ...
Hello,I have a question regarding switch updates.Since we have two locations with multiple floors and two patch rooms per floor, I would like to split the updates.To make the process more time-efficient, I would like to upload the new IOS-versions to...
Hi,This has been working fine up until now.All access switches (Catalyst 9300L) show the certificate status as "Active".Catalyst Center version: 2.3.7.10The two border routers are Catalyst C9500-24Y4C switches. Both switches are currently running IOS...
I currently have version 2.3.7.10.70209.10. Can I perform the entire process while the system is running? And yes, it would be neither the master nor the secondary.
Great—that turned out to be the problem in the end: the missing synchronization between the startup and running states. Now that it's synced, everything looks great. Unfortunately, I couldn't find that written down anywhere.
yes you`re right. It adds "C" automatically.below you see, what i have configured on the template. My compliance check result me this, picture below.On the Switch itself, the whole thing looks different. It's unclear whether the Switch still rewrite...
Hi,I have now configured the following: banner motd #***************************************************** !!Device is managed by DNA Center!! ******** DO NOT ALTER ANY CONFIGURATION ON CLI ****************************************************...