We have upgraded our APICs to 5.3(2f) and would like to start the switch upgrades. We have 2 Spines and Several Leafs but not all of the Leafs are in a VPC. I have a TAC case open but would like "real" world experience if possible as well. I would like to get the Spines upgraded first so I can do a group of VPC switches or standalones during future maintenance windows. We have several FEX's that the end devices are single homed devices so I have to coordinate all service owners on the that fex before we upgrade the Leaf it is attached to.
So my question is can I go ahead and upgrade the 2 Spines this weekend and then upgrade the Leafs in groups over the next week.
Thanks,
Joe