Hi, 

Is there any special procedure for moving APIC connection to new leaf switches ? 

Lets say, curretly 

  • APIC --> leaf-A & leaf-B
  • move it to 
  • APIC --> leaf-C & leaf-D

if we simply unplug the cables and re-connect them to new leafs will that work ?

1 Accepted Solution

Accepted Solutions

RG02469
Level 1
Level 1

I got the answer,

the APIC has to be decommissioned first, moved to target leafs and re-commission.

View solution in original post

1 Reply 1

RG02469
Level 1
Level 1

I got the answer,

the APIC has to be decommissioned first, moved to target leafs and re-commission.