jefffestejo
Beginner
Beginner

I am trying to configure jobs dependencies to kick off if the jobs completed normally or abnormally. I am looking to use the status "completed". 

By using "completed" will this satisfy either normal or abnormal

 

Thanks

1 Accepted Solution

Accepted Solutions

Derrick Au
Enthusiast
Enthusiast

Hi Jeff,

 

That is correct. When job dependency is set to completed, then it satisfied when job either completes normally or abnormally.

 

BR,

Derrick Au

View solution in original post

3 Replies 3

It will satisfy in both normal and abnormal completion

Hi Dinesh,

 

I believe you've beat me to the punch line. I was still fiddling around with my spell checker at that moment :-]

 

Cheers,

Derrick Au

Derrick Au
Enthusiast
Enthusiast

Hi Jeff,

 

That is correct. When job dependency is set to completed, then it satisfied when job either completes normally or abnormally.

 

BR,

Derrick Au