I am trying to configure jobs dependencies to kick off if the jobs completed normally or abnormally. I am looking to use the status "completed".
By using "completed" will this satisfy either normal or abnormal
Thanks
Solved! Go to Solution.
04-29-2015 10:39 AM
Hi Jeff,
That is correct. When job dependency is set to completed, then it satisfied when job either completes normally or abnormally.
BR,
Derrick Au