Report retention in PeopleSoft - Tidal jobs

Lumi Mihalcea
Level 1
Level 1

I am having an issue with the report retention on PeopleSoft. If I run a job in Tidal, the expiration is set to 7 days. If I run the same job in PS, same user-id, the retention is 90 days, which is the actual retention set up in PS. Did anybody run into this issue? Thanks!               

1 Reply 1

Lumi Mihalcea
Level 1
Level 1

Got great help from John Laird at Tidal support - Thank you John!!! and problem is fixed - here is his answer:

Yes, I found out that this was added in 8.5x support. There is now a parameter which you can set the retention through Tidal. The default is 7 days. Just add it to the connection options tab in the configuration parameters. Disable/enable when you get a chance to ensure the new configuration takes effect. The following is the parameter to add to the configuration parameter.

RETENTIONDAYS=<#ofdays>

RETENTIONDAYS

7

The number of days the process result is viewable in PeopleSoft Process Monitor before it is purged by Process Scheduler. The value populates the PeopleTools table field SPRCSQUE.PT_RETENTION_DAYS at runtime.