12-06-2016 07:52 AM - edited 03-01-2019 09:24 AM
I have a job that reruns every 5 minutes but if it completes abnormally the job stays in that status. In Tidal 5.3.1 this job would automatically reset itself and try rerunning in 5 minutes. I don't see anything different in the way the jobs are set up between the two environments. Does anyone know how to resolve this issue so that the job automatically resets.
12-06-2016 10:03 AM
Hello Frederick,
Are you stating that once the 1st failure happens, all other attempts automatically are noted as ' Completed Abnormally'?
snapshot your Schedule & Options tab so we can take a peak.
12-06-2016 10:16 AM
12-06-2016 03:05 PM
In your master database run the following (I show it in MSSQL):
select * from sysval where sysval_id = 93
If it is set to 'Y' then jobs will only rerun on 'completed normally'. If it is set to 'N' then the jobs should rerun even if it completed abnormally.
12-07-2016 11:13 AM
Hey Mike,
Is your SQL update the same as going to the System Configuration/ OTHER tab and putting a check box on 'Allow Job Rerun on any completed Normally and Completed Abnormally States"? just curious for my own information. thanks in advance.