03-01-2017 02:44 AM
Hi there,
My customer (in the UK) wants to order the SNS 3515 appliance but is facing 49 day lead times (as seen on CCW).
What other alternatives do I have to provide ISE faster?
Could I provide the VM temporarily then the customer transitions to physical hardware (SNS) once it is delivered?
Thank you,
Arron
Solved! Go to Solution.
03-01-2017 08:04 AM
Arron,
Yes. The customer can use a VM while they wait for physical appliances to arrive then migrate over.
Regards,
-Tim
03-01-2017 08:04 AM
Arron,
Yes. The customer can use a VM while they wait for physical appliances to arrive then migrate over.
Regards,
-Tim