Virtual ISE - VMware Resource Upgrade

gacs
Cisco Employee
Cisco Employee

Hi Team,

If we install the admin/monitoring nodes based on a smaller OVA template

(like the 3495 PAN/MNT OVA template with 32 GB RAM, 8 Core)

can we increase the memory/CPU at a later time (that requires a reboot) without reimaging the node and migrate to 3595 ?

Or increasing memory/CPU (at a later phase) is only supported if the VM was installed based on ISO?

Thank you!

Best regards, Gyorgy

1 Accepted Solution

Accepted Solutions

Timothy Abbott
Cisco Employee
Cisco Employee

Hi,

You should be able to adjust memory and CPU resources later on.  Just be sure to reset the reservations as required.

Regards,

-Tim

View solution in original post

2 Replies 2

Timothy Abbott
Cisco Employee
Cisco Employee

Hi,

You should be able to adjust memory and CPU resources later on.  Just be sure to reset the reservations as required.

Regards,

-Tim

hslai
Cisco Employee
Cisco Employee

Adding to Tim's, please also tweak the personas of the modified VMs, as some ISE resource allocations are only re-adjusted during install/setup or persona changes.