03-22-2012 11:52 AM - edited 03-10-2019 06:56 PM
Hi folks,
What would be the right procedure to upgrade ACS 5.1 to 5.3 ?
Our client needs to a smooth upgrade to the latest and greatest 5.3 version. The plan is use a backup made on 5.1 and install it on the new system.
Should the new system be running version 5.1 or I can start with 5.2 to save time for the upgrade?
Eugene
03-22-2012 12:04 PM
I recommend the following
- Take a backup on ACS 5.1
- Clean install of ACS 5.3
- Install ACS 5.3 patch 2: this has some fixes for the upgrade process
- restore the backup of ACS 5.1. After restore process completes upgrade process will start
03-22-2012 02:02 PM
The patch 2 installation went OK, failing on the restore part.
The database file is 206 MB of size. Isn't it too much to pull over FTP?
ACS53/admin# restore DB_Backup-120320-1607.tar.gpg repository REPO
Restore requires a reboot to successfully complete. Continue? (yes/no) [yes] ?
% Failure occurred during request
And the FTP server doesn't report any error. The connection is made and closes:
20:53:43 192.168.1.160 [8]USER boss 331 0
20:53:43 192.168.1.160 [8]PASS - 230 0
20:53:52 192.168.1.160 [8]sent /DB_Backup-120320-1607.tar.gpg 226 0
20:53:52 192.168.1.160 [8]QUIT - 226 0
Any ideas ?