I need help on CISCO MDS switch migration. I have three MDS 9396s Switches in the same fabric. We are planning to remove EOM core switch of the fabric.
A-Principal
B-Edge
C-Edge
We have ISL portchannels between A to B and A to C. B and C are not directly connected. Is that possible if I can create port channel between B and C also without removing the existing portchannels between A to B and A to C ?
If it is possible than I simply move FC cables from A to B/C and disable the PC between A to B and A to C.
Please suggest and help me to plan the migration.
Thanks
Manoj Kumar