Good day.
We need to move a pair of C93180YC-EX to a new rack, they have no server connections rather just uplinks to Spines. What is the proper graceful procedure to complete this rather than just power them off and move then power back on? Thanks.
Leo
Solved! Go to Solution.
11-16-2023 07:05 AM - edited 11-16-2023 07:06 AM
Hi Leo,
The proper way would be to decomission (decomission only) the switch. Then you can safely power it down, re-locate it, and re-power it back up. Once complete you just "commission" the switch back to service.
Robert
11-16-2023 07:05 AM - edited 11-16-2023 07:06 AM
Hi Leo,
The proper way would be to decomission (decomission only) the switch. Then you can safely power it down, re-locate it, and re-power it back up. Once complete you just "commission" the switch back to service.
Robert
11-16-2023 07:38 AM
Thanks Robert.
Leo