Move C93180yc-EX leaf to a new rack

a12288
Level 3
Level 3

Good day.

We need to move a pair of C93180YC-EX to a new rack, they have no server connections rather just uplinks to Spines. What is the proper graceful procedure to complete this rather than just power them off and move then power back on? Thanks.

Leo

1 Accepted Solution

Accepted Solutions

Robert Burns
Cisco Employee
Cisco Employee

Hi Leo,
The proper way would be to decomission (decomission only) the switch.  Then you can safely power it down, re-locate it, and re-power it back up.  Once complete you just "commission" the switch back to service.

RobertBurns_1-1700147157931.png

 

Robert

View solution in original post

2 Replies 2

Robert Burns
Cisco Employee
Cisco Employee

Hi Leo,
The proper way would be to decomission (decomission only) the switch.  Then you can safely power it down, re-locate it, and re-power it back up.  Once complete you just "commission" the switch back to service.

RobertBurns_1-1700147157931.png

 

Robert

Thanks Robert.

Leo