ACE30 not powering up

Yousef Askool
Level 1
Level 1

Dear Teams .

I have ACE 30 module which is runing on SW 6500 in VSS mode, Vr. 15.0.2 with enugh power avilable ( 2550 W )   , i have insert the module at slot number 7 , the issues am facing it's desribe below :

7/0 ACE Expansion Card  1       ACEMOD-EXPN-DC     1.1    PwrDown

7/1 ACE Expansion Card  2       ACEMOD-EXPN-DC       1.1    PwrDown

And if i take out the blade and insert it again it's work for some time then goes down . here is the consle messages before it goes down  :

.ACE platform with 2097152 Kbytes of main memory

.Loading disk0:c6ace-t1k9-mz.A4_1_0.bin.  Please wait ....

Uncompressing Linux...

Starting the kernel...

^[[A

INIT: version 2.85 booting

Configuring network interfaces.

FAT FS is ok

New registry installed.

INIT: Entering runlevel: 3such f

setting /usr/sbin/ipmaddr add 01:00:81:00:00:00 dev eth0

Firmware compiled 22-Jul-10 14:50 by jcbryant Build [25856]

Starting CDE setup

CDE 1 revision ID 050a

CDE 2 revision ID 0501

Finished CDE setup

ACE Daughter boards DB1 present DB2 present.

Powering up DC1 (of DC1/DC2)...  Succeeded..

DC1 present, checking if 'DC Rommon' needs upgrade...

DC1 'DC Rommon' is latest, no upgrade needed.

DC1 present, checking if 'DC Controller' needs upgrade...

DC1 'DC Controller' is latest, no upgrade needed.

Powering up DC2 (of DC1/DC2)...  Succeeded..

DC2 present, checking if 'DC Rommon' needs upgrade...

DC2 'DC Rommon' is latest, no upgrade needed.

DC2 present, checking if 'DC Controller' needs upgrade...

DC2 'DC Controller' is latest, no upgrade needed.

Waiting for NP's to boot

Image Download for NP1 Started.

Image Download for NP3 Started.

.............

NP1 Image DownLoad Complete!!!

NP3 Image DownLoad Complete!!!

Image Download for NP2 Started.

Image Download for NP4 Started.

......................................

NP4 Image DownLoad Complete!!!

NP2 Image DownLoad Complete!!!

NP1 boot complete.

NP2 boot complete.

NP3 boot complete.

NP4 boot complete.

Waiting for 3 seconds to enter setup mode...

Certificate & key are up to date

Regards

Yousef Askool .

2 Replies 2

ajayku2
Cisco Employee
Cisco Employee

Hi Yousef,

As per the documentation

Slot 7 is reserved for the supervisor engine. Please try to put it in different slots as suggested by below document.

If a redundant supervisor engine is not required, slots 1 through 6 and slots 8 through 13 are available for modules.

http://www.cisco.com/en/US/docs/interfaces_modules/services_modules/ace/vA4_1_0/installation/note/ace30inote.html#wp42094

Please go through the following notes :

All Catalyst 6500 series switches and Cisco 7600 series routers support  hot swapping, allowing you to install, remove, and replace modules  without turning off chassis power. For more information on removing the  modules from a switch, see the "Removing a Module" section.

When the software detects that a module has been installed or removed,  it automatically runs diagnostic and discovery routines, acknowledges  the presence or absence of the module, and resumes switch operation.

The Catalyst 6503-E switch, Cisco 7603 router, or Cisco 7603-S router  chassis has three horizontal slots. The Catalyst 6504-E switch, Cisco  7604 router, or Cisco 7604-S router chassis has four horizontal slots.  In these chassis, the slots can be used as follows:

Slot 1, the top-most slot, is reserved for the supervisor engine.

Slot 2 can be used for a redundant supervisor engine.

If a redundant supervisor engine is not required, the following slots are available for modules:

Slots 2 and 3 on the 3-slot chassis

Slots 2 through 4 on the 4-slot chassis

Empty slots require filler panels to maintain consistent airflow through the chassis.

The Catalyst 6509-V-E switch, the Cisco 7609 router, or the Cisco 7609-S  router chassis has nine vertical slots, which are numbered 1 to 9 from  right to left. Install vertical modules with the component side facing  to the right. In these chassis, the slots can be used as follows:

Slot 5 is reserved for the supervisor engine.

Slot 6 can be used for a redundant supervisor engine.

If a redundant supervisor engine is not required, the following slots are available for modules:

Slots 1 through 4 and slot 6 on the 6-slot chassis

Slots 1 through 4 and slots 6 through 9 on the 9-slot chassis

Empty slots require filler panels to maintain consistent airflow through the switch chassis.

The Catalyst 6513 switch or Cisco 7613 router chassis has 13 horizontal  slots. In these chassis, the slots can be used as follows:

Slot 7 is reserved for the supervisor engine.

Slot 8 can be used for a redundant supervisor engine.

If a redundant supervisor engine is not required, slots 1 through 6 and slots 8 through 13 are available for modules.

Empty slots require filler panels to maintain consistent airflow through the chassis.

Thanks Ajay .

the issue caused by image ver . since it's was runing ver 4.0 and the 6500 sup2d , an image upgrade solve the problem ,