In the PS job definition, under the schedule tab, click on 'forecast' and it shows the date that the jobs are forecast to run. When I create/compile a
forecast schedule, the jobs do not show in the forecast schedule. Any suggestions. Thanks.
07-07-2015 09:59 AM
This discussion has been reposted to the Tidal Enterprise Scheduler community
07-08-2015 10:03 AM
Thanks Rosaho
Hi Francestrotter,
Are you still having this issue? If so, check if GCC02 has a calendar that is defined with a larger number of days than the calendar used within your PS job definition. If GCC02 is blank or contains a subset of calendar days used within your PS job definition, then this job will never get scheduled/forecasted properly.