04-23-2025 08:05 PM
Hi Community Members,
Pls guide on how should i perform the memory upgrade from 32 to 96Gb for admin node. I have distributed deployment with two admin nodes i.e. one ppan on DC-A and span on DC-B.
Regards,
MT
Solved! Go to Solution.
04-25-2025 05:27 AM
- @M Talha - It will not cause any outage ; also since that operation doesn't take much time , there is no need to promote the secondary admin to primary ,
M.
04-23-2025 10:53 PM
- What ISE hardware are you using ?
M.
04-23-2025 11:25 PM
I am using VM's with version 3.3 patch 4
04-23-2025 11:44 PM
- For an ISE VM you only need to shutdown the (a) node, change the memory in the hypervisor (settings for the VM); and
boot it up again; afterwards issue the command show application status ise
(check if everything is normal)
M.
04-25-2025 05:13 AM
@marce1000 before I proceed with memory upgrade of primary admin node I have to promote secondary admin to primary is my understanding correct ? Secondly once I shutdown the primary admin once the secondary admin takes primary role does it will cause any outage ?
04-25-2025 05:27 AM
- @M Talha - It will not cause any outage ; also since that operation doesn't take much time , there is no need to promote the secondary admin to primary ,
M.
04-25-2025 05:46 AM
Thanks a lot @marce1000