07-21-2022 05:43 AM
Hi Guys,
I have 5x nodes running in VM in distributed deployment mode (PAN/PMnT, SAN/SMnT, 3x PSNs). Our old VM servers will need to be migrated to the new VM servers which means the ISE should be migrated also to the new VM servers. Connectivity between the old VM servers and new VM servers are not an issue.
My plan is to have 2x phase approach, the 1st phase will be the SAN and 1x PSN then the 2nd phase will be the PAN and the other PSNs.
My question now is about the license as we are using Traditional License.
Thank you
07-21-2022 10:29 AM
Why not just vMotion them to the new hosts?
07-21-2022 07:31 PM
Hi @ahollifield , my customer does not want to use the cold migration strategy because they told me it does not work the last time they did that and they want to have at least a minimal downtime that is why we are building a new one in parallel per phases.
07-22-2022 04:44 AM - edited 07-22-2022 04:51 AM
It does work as long as the ISE nodes are shutdown when they are moved. Hot VMotion is only supported from 3.1. What exact issues did they have last time? I also don't think phase 2 of your approach would work. How are you planning on building out a new PAN? Or are you making the new SAN the PAN in Phase 2?