12-02-2020 05:55 AM
Hi all
I should install a new Catalyst 9606 quad-supervisor in stackwise virtual configuration
The customer ask to me if is it possible to remove a supervisor active failed and insert a new one without power down the chassis or, anyway, doesn't interrupt the service.
I've confirmed that this is possible and should be no outage of the network.
About this, is there a document in the Cisco literature that confirm what I said to the customer?
Thank in advance and excuse me if this question seems a trivial question
Fabrizio
12-02-2020 06:03 AM
Presumably the document confirms your assertions.
M.
12-04-2020 07:40 AM
Hi marce1000
You alright
but I' m only looking for something on which it is wrote,
a note, a document and so on.
Until now I 've found nothing.
Thx
Discover and save your favorite ideas. Come back to expert answers, step-by-step guides, recent topics, and more.
New here? Get started with these tips. How to use Community New member guide