win 2003 r2 server
LMS 3.2
RME 4.3.1
When a netconfig job (and SWIM job for that matter) executes, I notice the job chages about 9 devices concurrently. The job is set for parallel changes. Is there a way to increase the number of concurrent modifications? I have to make changes on ~1500 switches and have 2 hour maintenance windows (trying to maximize time efficiency and minimize outage windows).
I am doing 2 netconfig jobs, 1 is adding 2 simple configurations, the second is a reload. the SWIM job is pretty standard.
If this is an application restriction, would creating multiple jobs to run at the same time help speed things up?