Have recently upgraded a pair of PIX 525s to 6.3(3)running in stateful failover and wish to load PDM on them. Queries I have:

1)As they are in production enviroment, do you have to reload the PIXes for PDM to work?

2) Is there a recommended method for installing PDM on a live PIX pair?

1 Accepted Solution

Accepted Solutions

shannong
Level 4
Level 4

1) No reload is necesssary.

2) The install is no different. The one thing to note is that you will need to enter config mode on the standby firewall which will generate a warning. You can ignore it. When you're done, use the write [standby command] on the active firewall as a precautionary measure.

View solution in original post

1 Reply 1

shannong
Level 4
Level 4

1) No reload is necesssary.

2) The install is no different. The one thing to note is that you will need to enter config mode on the standby firewall which will generate a warning. You can ignore it. When you're done, use the write [standby command] on the active firewall as a precautionary measure.