10-30-2014 02:34 AM - edited 03-10-2019 10:09 PM
Hello Community,
I administer an ISE installation with two nodes (I am not an ISE Specialist, my job is just to manage the user/mac-adresses... but now I have to move my ISE Nodes from one VMWare Cluster to another VMWare Cluster.
(Both VMWare environments are connected to our enterprise network, but are different environments. vMotion not possible)
I would shutdown ISE02, move it to our new VMWare environment and start it again.
Than I would do this with our ISE01 Node...
Are there any best practises for doing this? (Shutdown application first, stopl replikation etc)?
Can I really simply reboot an ISE Node - or have I consider something bevor I doing this? After I doing this?
Any tasks after reboot?
Thank you for any answer!
ISE01
Administration, Monitoring, Policy Service
PRI(A), SEC(M)
ISE02
Administration, Monitoring, Policy Service
SEC(A), PRI(M)
Solved! Go to Solution.