Hi all,
We just purchased a new 9509 to replace our older 9509. I would like to migrate all of the zoneing information from the old switch to the new switch so I can move my host connections over intact.
We have a mix of Win, Linux and HP-UX.
I am under the assumption all I have to do is the following:
- •1. Create new vsan on new switch to match the existing switch.
- •2. Make sure the new switch has a different domain ID
- •3. Add all of the new ports to the new vsan
- •4. Enable all of the ports
- •5. ISL the two switches together
- •6. Verify the zone information carried over to new switch
- •7. Move host connections to new switch
- •8. Disconnect the old switch.
Will someone please let me know if I am heading down the correct path?