Hi all have a question presently running UCX10.5.1 want to upgrade to 11.5.3SU3A there is a memory change from 6 G to 8G im thinking i could shut down vm`s change memory to 8 power back up and do the upgrade i have a tac case ongoing and being told by tac i have to build 2 new vm`s with the 11.5.1 matching ova and do a drs restore .
Not sure why you would have to build a new cluster just to increase the memory for a upgrade.
Any thoughts would be appreciated ????
I have had similar upgrade on cer 10.5.1 to 11.5.1 without any problems shutting them down to increase the memory and preforming the upgrade ...
Solved! Go to Solution.
10-30-2017 01:13 PM
Assuming that is the ONLY change (add vRAM), and you DO NOT require to modify the vCPUs, then that's supported
Support for adding virtual hardware resources (similar to moving from a less powerful server to a more powerful server, such as MCS 7825 -> MCS 7845) depends on which resource, and which UC product:
10-30-2017 01:13 PM
Assuming that is the ONLY change (add vRAM), and you DO NOT require to modify the vCPUs, then that's supported
Support for adding virtual hardware resources (similar to moving from a less powerful server to a more powerful server, such as MCS 7825 -> MCS 7845) depends on which resource, and which UC product: