CUCM 11.X MIGRATION FROM OLD BE6K TO NEW BE6K

Vinod.s
Level 3
Level 3

Hi All,

 

We are planning to buy new BE6K and currently we have cucm unity and uccx 11.5 .

Please suggest steps/process for this migration.

Also new be6k is comes with esxi 7.0 so cucm unity and uccx 11.5 support this esxi version?

 

Thanks in advance.

2 Replies 2

What i understood is you are planning to move from OLD box to NEW box on same version.   I would suggest to move to version 12.5.

 

Regarding migrations steps, Go through the below documents and you have all information regarding the migrations/upgrades.

  • Upgrade and Migration
  • Readme
  • Compatibility matrix

CUCM Guides

https://www.cisco.com/c/en/us/support/unified-communications/unified-communications-manager-callmanager/products-installation-guides-list.html

Unity Guides

https://www.cisco.com/c/en/us/support/unified-communications/unity-connection/series.html#InstallandUpgrade

 

Link to Cisco Collaboration Virtualization

https://www.cisco.com/c/dam/en/us/td/docs/voice_ip_comm/uc_system/virtualization/cisco-collaboration-virtualization.html



Response Signature


Hi Nithin,

 

I already checked this doc.. as per cucm 11.5 vertualization doc esxi 7.0 not supported...

 

Correct if i m wrong.