09-30-2019 06:59 AM
10-01-2019 07:04 PM - edited 10-01-2019 07:20 PM
Regards,
Alex
10-01-2019 07:46 PM
10-01-2019 09:16 PM - edited 10-01-2019 09:21 PM
Hi SYGY,
I'm having difficulty understanding your second paragraph. Do you mind rephrasing your thought? A diagram of your use-case would be helpful as well in understanding the premise of your situation.
As for your question "If we only need to restart this primary device, is there a way to avoid traffic interruption?", only mitigation to traffic interruption is possible on the n3ks. A complete avoidance of traffic interruption is not possible on this series of nexus devices. Reload of software in a stateful manner can however be accomplished on certain builds of the n5k, n7k, and n9k series. I would talk to your Cisco accounts manager if your network would benefit from improved high availability features as well as others like VDC, modularity, ACI compatibility, etc.
Regards,
Alex
10-01-2019 09:33 PM
Find answers to your questions by entering keywords or phrases in the Search bar above. New here? Use these resources to familiarize yourself with the community: