03-28-2016 03:28 PM - edited 03-01-2019 09:21 AM
I have two Job groups JG1 and JG2 and my requirement is to make sure that both Job groups must be mutually exclusive.
Please suggest.
03-29-2016 10:05 AM
So, in the scenario you mentione above, what is the expected sequence of job runs ?
Since Exp1 is already running, Exp2 should not run at all ? or should Exp2 wait for Exp1's completion and run ? and when does HC1 run ideally ?
03-29-2016 11:16 AM
Hi Dinesh,
Exp and HC job groups are launched on adhoc basis. There is no specific schedule.
If Exp1 is running and Exp2 and HC1 are eligible to run and are waiting, then only of them should run first and once completed the other should run.
At any point of time only one instance either Exp's Job group or HC's Job group instance can run. They cannot run parallel.
Hope this clarifies :-)