01-25-2021 02:48 AM
Hi, I'm trying to upgrade my N7K-7010 from 6.2.20 to 7.3(5).D1.1.
While reading the document, I have a question.
Is it necessary to upgrade the line card, Standby Supervisor, and Active Supervisor separately for EPLD upgrade?
The working Step I think is 1. OS Upgrade. 2. This is an entire EPLD upgrade.
I want to know if there is a problem even if I upgrade at once with the install all epld command after OS upgrade.
Thank you.
Solved! Go to Solution.
01-25-2021 11:37 PM
- I would follow the advice from the guide.
M.
01-25-2021 03:58 AM
https://www.cisco.com/c/en/us/td/docs/switches/datacenter/sw/6_x/epld/epld_rn_62.html
-Check Table 5 and look at the example commands, acting accordingly will probably result in minimum risk. As far as the need to upgrade EPLD , check this paragraph : Deciding When to Upgrade EPLDs
M.
01-25-2021 07:57 AM
Hello, marce
Thank you for answer.
I saw the same document.
As a result of checking, it seems that the EPLD of the linecard currently being used does not need to be upgraded to 1.006.9(F248XP-25E).
I think you only need to upgrade for Dual Supervisor.
The chassis is also redundant, so it doesn't matter because it provides failover. The Guide tells you to perform Active upgrade after Standby upgrade. Is it okay to do EPLD Upgrade of Active/Standby Supervisor at once?
01-25-2021 11:37 PM
- I would follow the advice from the guide.
M.
01-28-2021 04:05 AM
hola espero te encuentres bien a continuación te envió el procedimiento para ejecutara esta actualización, recuerda que esta actualización es no disruptiva , tu equipo no será apagado mientras se actualiza lo que no deberá afectar la operación de tu negocio,
recuerda darle click en la estrella esto motiva a continuar aportando material a la comunidad.
Discover and save your favorite ideas. Come back to expert answers, step-by-step guides, recent topics, and more.
New here? Get started with these tips. How to use Community New member guide