Hi Folks

Pls Have a Look to the Attachment,is okay in term in Redunsancy at the access Layer where 3750G Exist,I considered 1 Link fiber form 1st witch to first CORE while 2nd Link form the third switch going to the 2nd CORE,please Advise

2 Replies 2

Latchum Naidu
VIP Alumni
VIP Alumni

Hi,

As long as you are running redundant protocol like HSRP and redundancy is working fine between both your core switches then the diagram is looks ok.

And the uplink ports as configured trunk ports you are fine with the diagram.

Please rate the helpfull posts.

Regards,
Naidu.

Hi Naidu!

I Won't run HSRP because  my CORE is VSS based