Hello,
From 8.6(x) to 8.6(x)
From 8.6(x) to 9.x
From 9.x to 9.x
From 10.0(1) to 10.x
Thank you for the assistance
06-13-2016 05:50 AM
Hi,
If you have a single node Unity Connection I would recommend you dealing with simple Refresh Upgrade and Change VM settings afterwards. I did it for a two-node CUC cluster from 8.6.2 to 10.5.2 and it was the best approach.
Even if it would work, PCD is worth it when you have to migrate systems (move from physical to virtual) or if you have plenty of nodes/clusters. CUC support seems to be rather limited, hence I kept the old approach and avoided PCD for Unity Connection.
Christoph
06-13-2016 07:21 AM
06-14-2016 01:24 AM
Yes, please follow that guideline and don't forget about the licensing.
If you have already the proper licenses for messaging installed on your CUCM / PLM you can simply connect CUC after successfull upgrade to the license manager.
Christoph
06-13-2016 06:37 AM
Hi there,
Just wanted to add a reference to the good notes from Cristoph (+5) Please see the attached bug;
06-13-2016 09:57 AM
Rob is spot on with that defect [+5], you cannot use PCD for CUC Refresh Upgrade. It had to be the traditional way i.e, either using CLI or OS Administration.
Regards
Deepak
06-15-2016 04:20 AM
Thank You Christoph , Rob and Deepak for the response..