Heads Up :
The post you are writing will appear in a public forum. Please ensure all content is appropriate for public consumption. Review the employee guidelines for the community here.
How do you onboard the 9200 and 9300 catalyst switches in hybrid mode? We would like to manage it from the cli as well as from the cloud. Can the switches firmware be updated from the cloud in hybrid mode? Can the switch really be fully managed from ...
We have a stack of 5 x 3850 switches. 3 switches are model WS-C3850-48T and 2 are model WS-C3850-24XS. Stack:Switch 1 - 3 WS-C3850-48TSwitch 4 - 5 WS-C3850-24XS The stack also has stack power (2 rings) configured. We would like to remove Switch 3 fr...
Would like to know which switch is best to make the root switch. I'm debating between SW3 and SW1. SW1 in our MDF will be the L3 switch. SW3 is an intermediate switch for fiber. All switches will be MS225s except SW3 which will be MS130 or MS390.Tha...
Sorry to take up some of your precious time but I have a small question. We have a 1gbps dedicated internet (Fiber) AT&T link and I'm trying to determine if the total load (inbound + outbound) is a little high for the link. Since this is full duplex ...
I'm having trouble accessing a user account (2 characters) and password (4 characters) created on a 9300 switch. This exact account was working fine on a 3850 switch. Were any changes made as far as minimum requirements for user accounts?
Management would like to consolidate the used ports and get rid of hardware that is no longer required. It's a 24x7 datacenter, so we have to minimize downtime as much as possible. POE is not used much.
I agree but that's not something that we can change easily. The wiring was already done and the long distances between LDFs and MDF would make it very expensive.