10-20-2008 06:53 AM - edited 03-15-2019 02:02 PM
I'm in the initial stages of planning a new CUCM 6.x cluster to replace our current production cluster at 4.1(3). This is centralized call processing for roughly 10 sites. We are going to create a new cluster and move sites in one-by-one.
When I actually start the first server build, is it acceptible to have the server in the same network as the production cluster? I don't want anything in the initial build(s) to impact the production environment.
Any other considerations or gotchas I might run into?
Thanks,
Ken
10-20-2008 07:16 AM
Sure, as long as the hostname and IP address is different. But if the hostname is different DMA migration will not be possible if that's what you are planning on.
Chris
10-20-2008 07:47 AM
Thanks very much. I don't think we're going to use the DMA. There are some design issues I'd like to clear up with a 'fresh' build.