07-21-2010 08:34 PM - edited 03-15-2019 11:50 PM
Need some recommendations as how to go by when migrating and upgrading from cucm 6.x cluster of 4 servers to 7.x with the hardware replacement. I've got a cisco documentation that describes replacement of one or more nodes in a cluster, however it talks about the version being the same.
I wonder, can the 7.x server retreive/restore from a backup file created from the 6.x server? if not what should be the strategy to accomplish that.
Any ideas would be highly appreciated.
07-29-2010 06:54 AM
Hello,
UCM Backups can only go exact version to exact version. What this means is that if you're running 6.1.3.1000-16 for example, you would need to restore to 6.1.3.1000-16. In a HW migration you have a couple options.
1. If your current publisher supports it, upgrade to the version you wish to ultimately migrate to then take backup and restore to same version on new hardware.
2. Install current version to new hardware, restore from backup then upgrade.
If the new hardware doesn't support the old version then you will need to upgrade to the highest version in the same train first before backup. For instance, if you're on 6.1.2, upgrade to 6.1.5, then install 6.1.5 on new hardware then upgrade to 7.1.
Be sure to keep in mind that you will also need to secure the correct licenses since any time you change HW the previous licenses will become invalid since they're tied to the MAC address of your system.
Let me know if you have further questions.
07-29-2010 06:58 AM
You can also use this matrix to see which software versions are compatible with which HW:
Complete Unified Communications Compatibility Docs are below:
http://www.cisco.com/en/US/products/sw/voicesw/ps556/products_device_support_tables_list.html
07-29-2010 06:05 PM
Thanks Mathew, this is helpful. 5 points for you.