I need your help and suggestion about how to design a new company site with the following information

2 main IT ROOMs : the first one with 2*9704 and 4 cisco 2960x , se second with one 9704 and 3 cisco 2960x

many branch rooms that contains 2960x and are connected either to IR rooms 1 or 2 with Fiber cables

 

1 Reply 1

balaji.bandi
Hall of Fame
Hall of Fame

Look at the CVD (old but you get fair idea how you can place the core and access switch ) - in your case collapsed core design should work.

https://www.cisco.com/c/dam/en/us/td/docs/solutions/CVD/Aug2014/CVD-CampusWiredLANDesignGuide-AUG14.pdf

Since you have a new Cat 9407 you can do build StackWise virtual :

https://www.cisco.com/c/en/us/products/collateral/switches/catalyst-9000/nb-06-cat-9k-stack-wp-cte-en.html