Hi Guys,
I have pair of C3850-48X switches in stackwise virtual stack and now node 2 is dead and need to be replaced with new one. I think I have correct steps for bringing new node into stack but just want to verify these before do it on production site.
So first thing is to put same software level and license into replacement device than the current switch 1 has. Then I was planning to follow below steps for node 2 configuration.
conf t
stackwise-virtual
domain 1
interface te1/0/1
stackwise-virtual link 1
interface te1/0/48
stackwise-virtual link 1
interface te1/0/47
stackwise-virtual dual-active-detection
wr mem
reload
immediately after reload command I will connect cables to node 2 (ports 1, 48 and 47) so that it can join the virtual stack.
In my opinion this should work for bringing node back into virtual stack but just want to verify if I am missing something here?
Br,
Mika
Solved! Go to Solution.
04-01-2019 07:57 AM
04-01-2019 07:57 AM
Discover and save your favorite ideas. Come back to expert answers, step-by-step guides, recent topics, and more.
New here? Get started with these tips. How to use Community New member guide